Showcase — Completed Works
Rollup last refreshed: 2026-07-11 02:05:34.314168
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Check Dam/Stop Dam
18 works
₹2.12 Cr sanctioned
₹2.06 Cr spent (97%)
02
Construction of Road and Culvert
12 works
₹1.46 Cr sanctioned
₹1.26 Cr spent (86%)
03
Repair & maint of Pond/ Tank
6 works
₹64.98 L sanctioned
₹60.07 L spent (92%)
04
Construction of Percolation Tank
4 works
₹59.34 L sanctioned
₹58.97 L spent (99%)
05
Construction of Bund
3 works
₹43.95 L sanctioned
₹42.78 L spent (97%)
06
Terracing
2 works
₹33.07 L sanctioned
₹30.53 L spent (92%)
07
Construction of Water Drain/Diversion Channel/Drainage/Field Channel
3 works
₹30.80 L sanctioned
₹29.42 L spent (96%)
08
Construction of Tank
3 works
₹29.93 L sanctioned
₹25.71 L spent (86%)
09
Repair & Maint of Check Dam/Stop Dam
2 works
₹27.22 L sanctioned
₹25.73 L spent (95%)
10
Works for Flood Control and Protection
2 works
₹23.22 L sanctioned
₹22.23 L spent (96%)