Showcase — Completed Works
Rollup last refreshed: 2026-07-11 02:05:34.314168
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Road and Culvert
13 works
₹94.87 L sanctioned
₹65.97 L spent (70%)
02
Construction of Trench
12 works
₹81.36 L sanctioned
₹73.35 L spent (90%)
03
Construction of Percolation Tank
18 works
₹67.57 L sanctioned
₹63.77 L spent (94%)
04
Construction of Check Dam/Stop Dam
23 works
₹59.53 L sanctioned
₹61.53 L spent (103%)
05
Construction of Well
17 works
₹52.08 L sanctioned
₹50.71 L spent (97%)
06
Construction of Tank
3 works
₹40.42 L sanctioned
₹40.20 L spent (99%)
07
Boulder Check/Gully Plug
224 works
₹32.20 L sanctioned
₹27.44 L spent (85%)
08
Cattle Shed
4 works
₹28.83 L sanctioned
₹28.77 L spent (100%)
09
Rural Housing
117 works
₹20.16 L sanctioned
₹19.76 L spent (98%)
10
Constr of Cement Concrete Roads
15 works
₹19.84 L sanctioned
₹17.07 L spent (86%)