Showcase — Completed Works
Rollup last refreshed: 2026-07-11 02:05:34.314168
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Trench
10 works
₹37.52 L sanctioned
₹32.34 L spent (86%)
02
Construction of Road and Culvert
6 works
₹33.68 L sanctioned
₹16.56 L spent (49%)
03
Rural Housing
138 works
₹30.76 L sanctioned
₹29.93 L spent (97%)
04
Constr of Cement Concrete Roads
47 works
₹28.26 L sanctioned
₹26.81 L spent (95%)
05
Plantation
8 works
₹15.78 L sanctioned
₹8.33 L spent (53%)
06
Constr of Aganwadi
3 works
₹8.09 L sanctioned
₹7.20 L spent (89%)
07
Cattle Shed
5 works
₹4.89 L sanctioned
₹4.82 L spent (99%)
08
Construction of Play field
2 works
₹4.74 L sanctioned
₹3,096 spent (1%)
09
Construction of Well
5 works
₹3.45 L sanctioned
₹1.05 L spent (31%)
10
Construction of Tank
1 works
₹3.33 L sanctioned
₹3.06 L spent (92%)