Showcase — Completed Works
Rollup last refreshed: 2026-07-11 02:05:34.314168
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Check Dam/Stop Dam
44 works
₹3.23 Cr sanctioned
₹3.01 Cr spent (93%)
02
Construction of Road and Culvert
17 works
₹1.34 Cr sanctioned
₹1.07 Cr spent (80%)
03
Plantation
24 works
₹1.25 Cr sanctioned
₹45.22 L spent (36%)
04
Construction of Trench
17 works
₹94.26 L sanctioned
₹87.99 L spent (93%)
05
Constr of Gabion
102 works
₹71.30 L sanctioned
₹43.23 L spent (61%)
06
Land Development
8 works
₹57.96 L sanctioned
₹48.98 L spent (85%)
07
Rural Housing
303 works
₹51.29 L sanctioned
₹43.98 L spent (86%)
08
Boulder Check/Gully Plug
53 works
₹49.60 L sanctioned
₹29.84 L spent (60%)
09
Construction of Bund
5 works
₹36.90 L sanctioned
₹33.89 L spent (92%)
10
Construction of Tank
4 works
₹34.39 L sanctioned
₹31.81 L spent (92%)