Showcase — Completed Works
Rollup last refreshed: 2026-07-11 02:05:34.314168
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Percolation Tank
8 works
₹65.79 L sanctioned
₹64.12 L spent (97%)
02
Construction of Well
32 works
₹61.51 L sanctioned
₹59.65 L spent (97%)
03
Construction of Check Dam/Stop Dam
26 works
₹58.24 L sanctioned
₹45.76 L spent (79%)
04
Plantation
50 works
₹55.32 L sanctioned
₹22.18 L spent (40%)
05
Construction of Tank
14 works
₹45.28 L sanctioned
₹44.25 L spent (98%)
06
Rural Housing
220 works
₹41.01 L sanctioned
₹40.58 L spent (99%)
07
Construction of Trench
52 works
₹30.69 L sanctioned
₹26.89 L spent (88%)
08
Construction of Road and Culvert
9 works
₹27.64 L sanctioned
₹12.04 L spent (44%)
09
Constr of Cement Concrete Roads
14 works
₹9.57 L sanctioned
₹9.01 L spent (94%)
10
Repair & Maint of Check Dam/Stop Dam
1 works
₹8.57 L sanctioned
₹8.51 L spent (99%)