Showcase — Completed Works
Rollup last refreshed: 2026-07-11 02:05:34.314168
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Road and Culvert
17 works
₹96.54 L sanctioned
₹67.09 L spent (69%)
02
Cattle Shed
2 works
₹38.33 L sanctioned
₹38.26 L spent (100%)
03
Plantation
9 works
₹32.87 L sanctioned
₹16.46 L spent (50%)
04
Construction of Check Dam/Stop Dam
9 works
₹32.34 L sanctioned
₹19.50 L spent (60%)
05
Rural Housing
172 works
₹31.39 L sanctioned
₹30.76 L spent (98%)
06
Land Development
20 works
₹17.55 L sanctioned
₹11.70 L spent (67%)
07
Constr of Cement Concrete Roads
10 works
₹17.01 L sanctioned
₹15.97 L spent (94%)
08
Construction of Trench
2 works
₹15.92 L sanctioned
₹12.75 L spent (80%)
09
Construction of Bund
2 works
₹13.90 L sanctioned
₹6.64 L spent (48%)
10
Boulder Check/Gully Plug
2 works
₹9.18 L sanctioned
₹7.47 L spent (81%)