Monitor — Ongoing Works
Rollup last refreshed: 2026-07-11 02:05:34.314168
Works ongoing
30
Sanctioned (pure scheme)
₹3.70 Cr
Expenditure since inception
₹1.67 Cr
Balance cost (unspent)
₹2.04 Cr
Wage ₹1.35 Cr · Material ₹68.73 L
Expenditure trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
Slowest spending this week — worth a look
Mandays trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Bund
14 works
₹1.97 Cr sanctioned
₹83.49 L spent (42%)
02
Construction of Tank
11 works
₹1.42 Cr sanctioned
₹74.52 L spent (52%)
03
Construction of Trench
1 works
₹14.63 L sanctioned
₹6.61 L spent (45%)
04
Boulder Check/Gully Plug
3 works
₹13.26 L sanctioned
₹1.61 L spent (12%)
05
Constr of GP Bhawan
1 works
₹3.31 L sanctioned
₹33,138 spent (10%)
06
Construction of Canal
0 works
₹0 sanctioned
₹0 spent (0%)
07
Construction of Check Dam/Stop Dam
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Crematorium
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Percolation Tank
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Recharge Pits
0 works
₹0 sanctioned
₹0 spent (0%)