Monitor — Ongoing Works
Rollup last refreshed: 2026-07-11 02:05:34.314168
Works ongoing
12
Sanctioned (pure scheme)
₹3.46 L
Expenditure since inception
₹1.19 L
Balance cost (unspent)
₹2.28 L
Wage ₹2.28 L · Material ₹0
Expenditure trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
Slowest spending this week — worth a look
Mandays trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Constr of Cement Concrete Roads
4 works
₹1.72 L sanctioned
₹73,272 spent (43%)
02
Rural Housing
7 works
₹1.64 L sanctioned
₹39,411 spent (24%)
03
Solid and Liquid Waste Management
1 works
₹10,000 sanctioned
₹5,967 spent (60%)
04
Construction of Crematorium
0 works
₹0 sanctioned
₹0 spent (0%)
05
Construction of Play field
0 works
₹0 sanctioned
₹0 spent (0%)
06
Construction of Road and Culvert
0 works
₹0 sanctioned
₹0 spent (0%)
07
Land Development
0 works
₹0 sanctioned
₹0 spent (0%)
08
Plantation
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Check Dam/Stop Dam
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Bund
0 works
₹0 sanctioned
₹0 spent (0%)