Monitor — Ongoing Works
Rollup last refreshed: 2026-07-11 02:05:34.314168
Works ongoing
20
Sanctioned (pure scheme)
₹1.33 Cr
Expenditure since inception
₹52.82 L
Balance cost (unspent)
₹80.41 L
Wage ₹30.76 L · Material ₹49.65 L
Expenditure trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
Slowest spending this week — worth a look
Mandays trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Road and Culvert
5 works
₹60.32 L sanctioned
₹37.92 L spent (63%)
02
Works for Flood Control and Protection
2 works
₹16.62 L sanctioned
₹10.50 L spent (63%)
03
Repair & maint of Road
1 works
₹14.99 L sanctioned
₹80,288 spent (5%)
04
Construction of Check Dam/Stop Dam
1 works
₹14.75 L sanctioned
₹50,388 spent (3%)
05
Roof Water Harvesting on gov/panchayat bldg
1 works
₹13.89 L sanctioned
₹59,058 spent (4%)
06
Constr of GP Bhawan
1 works
₹7.50 L sanctioned
₹1.43 L spent (19%)
07
Construction of Water Drain/Diversion Channel/Drainage/Field Channel
1 works
₹4.15 L sanctioned
₹50,388 spent (12%)
08
Rural Housing
2 works
₹46,980 sanctioned
₹12,528 spent (27%)
09
Community Sanitary Complex
1 works
₹43,000 sanctioned
₹32,886 spent (76%)
10
Construction of Recharge Pits
1 works
₹6,600 sanctioned
₹6,528 spent (99%)