Monitor — Ongoing Works
Rollup last refreshed: 2026-07-11 02:05:34.314168
Works ongoing
46
Sanctioned (pure scheme)
₹62.84 L
Expenditure since inception
₹15.71 L
Balance cost (unspent)
₹47.13 L
Wage ₹20.08 L · Material ₹27.05 L
Expenditure trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
Slowest spending this week — worth a look
Mandays trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Well
8 works
₹33.58 L sanctioned
₹9.05 L spent (27%)
02
Construction of Tank
3 works
₹10.62 L sanctioned
₹3.88 L spent (37%)
03
Construction of Check Dam/Stop Dam
2 works
₹8.75 L sanctioned
₹86,326 spent (10%)
04
Rural Housing
30 works
₹7.05 L sanctioned
₹89,505 spent (13%)
05
Plantation
1 works
₹1.45 L sanctioned
₹31,344 spent (22%)
06
Constr of Aganwadi
1 works
₹99,000 sanctioned
₹63,884 spent (65%)
07
Constr of Cement Concrete Roads
1 works
₹40,000 sanctioned
₹6,318 spent (16%)
08
Construction of Crematorium
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of NADEP/Vermi Compost Pit
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Percolation Tank
0 works
₹0 sanctioned
₹0 spent (0%)