Monitor — Ongoing Works
Rollup last refreshed: 2026-07-11 02:05:34.314168
Works ongoing
9
Sanctioned (pure scheme)
₹11.95 L
Expenditure since inception
₹3.54 L
Balance cost (unspent)
₹8.41 L
Wage ₹4.44 L · Material ₹3.97 L
Expenditure trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
Slowest spending this week — worth a look
Mandays trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
2 works
₹5.09 L sanctioned
₹77,790 spent (15%)
02
Construction of Well
2 works
₹4.85 L sanctioned
₹2.42 L spent (50%)
03
Farm Pond
1 works
₹1.17 L sanctioned
₹204 spent (0%)
04
Rural Housing
3 works
₹70,470 sanctioned
₹34,713 spent (49%)
05
Construction of Check Dam/Stop Dam
1 works
₹14,024 sanctioned
₹0 spent (0%)
06
Constr of GP Bhawan
0 works
₹0 sanctioned
₹0 spent (0%)
07
Construction of Bund
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Crematorium
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Embankment
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of NADEP/Vermi Compost Pit
0 works
₹0 sanctioned
₹0 spent (0%)