Monitor — Ongoing Works
Rollup last refreshed: 2026-07-11 02:05:34.314168
Works ongoing
14
Sanctioned (pure scheme)
₹55.11 L
Expenditure since inception
₹19.08 L
Balance cost (unspent)
₹36.04 L
Wage ₹11.82 L · Material ₹24.22 L
Expenditure trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
Slowest spending this week — worth a look
Mandays trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Check Dam/Stop Dam
1 works
₹18.33 L sanctioned
₹12.64 L spent (69%)
02
Construction of Road and Culvert
1 works
₹17.90 L sanctioned
₹8,619 spent (0%)
03
Plantation
1 works
₹6.78 L sanctioned
₹2.52 L spent (37%)
04
Culvert
2 works
₹5.34 L sanctioned
₹2,652 spent (0%)
05
Constr of Cement Concrete Roads
3 works
₹2.83 L sanctioned
₹1.70 L spent (60%)
06
Constr of Aganwadi
1 works
₹1.80 L sanctioned
₹1.75 L spent (97%)
07
Solid and Liquid Waste Management
1 works
₹1.77 L sanctioned
₹1,326 spent (1%)
08
Rural Housing
1 works
₹23,490 sanctioned
₹21,924 spent (93%)
09
Constr of GP Bhawan
1 works
₹11,000 sanctioned
₹1,326 spent (12%)
10
Construction of NADEP/Vermi Compost Pit
1 works
₹2,000 sanctioned
₹204 spent (10%)