Monitor — Ongoing Works
Rollup last refreshed: 2026-07-11 02:05:34.314168
Works ongoing
46
Sanctioned (pure scheme)
₹32.32 L
Expenditure since inception
₹17.57 L
Balance cost (unspent)
₹14.76 L
Wage ₹8.27 L · Material ₹6.49 L
Expenditure trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
Slowest spending this week — worth a look
Mandays trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Well
5 works
₹11.43 L sanctioned
₹3.29 L spent (29%)
02
Rural Housing
35 works
₹8.22 L sanctioned
₹3.86 L spent (47%)
03
Works for Flood Control and Protection
1 works
₹6.00 L sanctioned
₹5.98 L spent (100%)
04
Construction of Crematorium
1 works
₹3.80 L sanctioned
₹3.42 L spent (90%)
05
Construction of Bund
1 works
₹1.07 L sanctioned
₹64,749 spent (61%)
06
Community Sanitary Complex
1 works
₹80,000 sanctioned
₹9,945 spent (12%)
07
Plantation
1 works
₹55,847 sanctioned
₹21,879 spent (39%)
08
Construction of Check Dam/Stop Dam
1 works
₹45,000 sanctioned
₹4,698 spent (10%)
09
Boulder Check/Gully Plug
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Toilets
0 works
₹0 sanctioned
₹0 spent (0%)