Rollup last refreshed: 2026-07-11 02:05:34.314168
Works ongoing
33
Sanctioned (pure scheme)
₹1.29 Cr
Expenditure since inception
₹53.02 L
Balance cost (unspent)
₹76.02 L
Wage ₹42.31 L · Material ₹33.71 L
Expenditure trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
Slowest spending this week — worth a look
Mandays trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Tank
3 works
₹71.81 L sanctioned
₹32.70 L spent (46%)
02
Construction of Well
7 works
₹26.97 L sanctioned
₹7.41 L spent (27%)
03
Farm Pond
3 works
₹13.53 L sanctioned
₹8.63 L spent (64%)
04
Plantation
3 works
₹7.41 L sanctioned
₹85,715 spent (12%)
05
Construction of Recharge Pits
1 works
₹5.37 L sanctioned
₹1,320 spent (0%)
06
Rural Housing
16 works
₹3.95 L sanctioned
₹3.40 L spent (86%)
07
Construction of Bund
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Canal
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Check Dam/Stop Dam
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Crematorium
0 works
₹0 sanctioned
₹0 spent (0%)