Monitor — Ongoing Works
Rollup last refreshed: 2026-07-11 02:05:34.314168
Works ongoing
8
Sanctioned (pure scheme)
₹20.69 L
Expenditure since inception
₹7.97 L
Balance cost (unspent)
₹12.72 L
Wage ₹6.67 L · Material ₹6.06 L
Expenditure trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
Slowest spending this week — worth a look
Mandays trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
2 works
₹9.08 L sanctioned
₹54,533 spent (6%)
02
Construction of Well
1 works
₹2.65 L sanctioned
₹415 spent (0%)
03
Boulder Check/Gully Plug
1 works
₹2.57 L sanctioned
₹1.77 L spent (69%)
04
Farm Pond
1 works
₹2.40 L sanctioned
₹2.07 L spent (86%)
05
Construction of Percolation Tank
1 works
₹2.00 L sanctioned
₹1.70 L spent (85%)
06
Construction of Check Dam/Stop Dam
1 works
₹1.74 L sanctioned
₹1.67 L spent (96%)
07
Rural Housing
1 works
₹24,795 sanctioned
₹21,024 spent (85%)
08
Construction of Play field
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Recharge Pits
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Road and Culvert
0 works
₹0 sanctioned
₹0 spent (0%)