Monitor — Ongoing Works
Rollup last refreshed: 2026-07-11 02:05:34.314168
Works ongoing
12
Sanctioned (pure scheme)
₹94.73 L
Expenditure since inception
₹53.25 L
Balance cost (unspent)
₹41.49 L
Wage ₹28.26 L · Material ₹13.22 L
Expenditure trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
Slowest spending this week — worth a look
Mandays trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Check Dam/Stop Dam
1 works
₹48.82 L sanctioned
₹41.45 L spent (85%)
02
Plantation
5 works
₹31.84 L sanctioned
₹7.28 L spent (23%)
03
Construction of Trench
2 works
₹9.12 L sanctioned
₹1.51 L spent (17%)
04
Construction of Well
1 works
₹2.46 L sanctioned
₹1.30 L spent (53%)
05
Farm Pond
1 works
₹2.00 L sanctioned
₹1.30 L spent (65%)
06
Rural Housing
2 works
₹49,590 sanctioned
₹41,328 spent (83%)
07
Construction of NADEP/Vermi Compost Pit
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Percolation Tank
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Recharge Pits
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Road and Culvert
0 works
₹0 sanctioned
₹0 spent (0%)