Monitor — Ongoing Works
Rollup last refreshed: 2026-07-11 02:05:34.314168
Works ongoing
11
Sanctioned (pure scheme)
₹44.84 L
Expenditure since inception
₹15.20 L
Balance cost (unspent)
₹29.63 L
Wage ₹10.44 L · Material ₹19.19 L
Expenditure trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
Slowest spending this week — worth a look
Mandays trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Percolation Tank
1 works
₹14.19 L sanctioned
₹42,840 spent (3%)
02
Construction of Well
6 works
₹14.15 L sanctioned
₹6.64 L spent (47%)
03
Construction of Check Dam/Stop Dam
1 works
₹8.40 L sanctioned
₹5.24 L spent (62%)
04
Plantation
1 works
₹4.08 L sanctioned
₹26,724 spent (7%)
05
Construction of building/workshed for SHG
1 works
₹3.00 L sanctioned
₹2.53 L spent (84%)
06
Goat Shelter
1 works
₹1.02 L sanctioned
₹9,540 spent (9%)
07
Construction of Play field
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Recharge Pits
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Road and Culvert
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Tank
0 works
₹0 sanctioned
₹0 spent (0%)