MGNREGA Works Dashboard
Admin login

Monitor — Ongoing Works

Rollup last refreshed: 2026-07-11 02:05:34.314168
to
Reset filters
Works ongoing
22
Sanctioned (pure scheme)
₹31.64 L
Expenditure since inception
₹23.75 L
Balance cost (unspent)
₹7.89 L
Wage ₹6.87 L · Material ₹1.02 L
Expenditure trend
₹6.00 Cr
This Week
₹7.23 Cr
Last Week
▼ 17% vs last week
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
Slowest spending this week — worth a look
  • DHAR — TIRLA−₹1.14 Cr
Mandays trend
-1,62,948
This Week
-2,14,690
Last Week
▲ 24.1%
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
Lowest mandays this week — worth a look
  • DHAR — KUKSHI-88,895

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Road and Culvert
1 works
₹19.39 L sanctioned
₹17.65 L spent (91%)
02
Construction of Crematorium
2 works
₹3.89 L sanctioned
₹3.51 L spent (90%)
03
Rural Housing
15 works
₹3.51 L sanctioned
₹1.42 L spent (40%)
04
Construction of Tank
1 works
₹3.47 L sanctioned
₹2,210 spent (1%)
05
Constr of Cement Concrete Roads
3 works
₹1.38 L sanctioned
₹1.15 L spent (83%)
06
Construction of Check Dam/Stop Dam
0 works
₹0 sanctioned
₹0 spent (0%)
07
Construction of NADEP/Vermi Compost Pit
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Other Community Building/Assets
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Percolation Tank
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Play field
0 works
₹0 sanctioned
₹0 spent (0%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. District Ongoing works Sanctioned Expenditure Balance cost Exp. %
1 ASHOK NAGAR 22 31.64 23.75 7.89
75%
Total 22 31.64 23.75 7.89
All 1 rows (zero-value rows hidden) ⇩ Export to Excel