Ongoing works

Works in progress: what they cost, what has been spent, and how fast spending is moving.

MGNREGA + VBGRAMGConstruction of Road and Culvert
66.6%
OF COST SPENT
₹20.86 Cr spent
of ₹31.34 Cr sanctioned
₹10.48 Cr still to spend
on 184 ongoing works
Works ongoing
184
Open the list of these works →
Sanctioned
₹31.34 Cr
Pure scheme (wage + material)
Expenditure since inception
₹20.86 Cr
66.6% of sanction
Balance cost (unspent)
₹10.48 Cr
Wage₹5.86 Cr
Material₹4.62 Cr
Trend · statewide

—
—
Slowest spending this week · worth a look
Sidhi — Sihawal −₹1.52 Cr
Top 10 new work types

Ranked by sanctioned cost

Breakdown

By block

Amounts in ₹ Crore