Ongoing works

Works in progress: what they cost, what has been spent, and how fast spending is moving.

MGNREGA + VBGRAMGLand Development
42.4%
OF COST SPENT
₹47.85 Cr spent
of ₹112.74 Cr sanctioned
₹64.89 Cr still to spend
on 2,181 ongoing works
Works ongoing
2,181
Open the list of these works →
Sanctioned
₹112.74 Cr
Pure scheme (wage + material)
Expenditure since inception
₹47.85 Cr
42.4% of sanction
Balance cost (unspent)
₹64.89 Cr
Wage₹38.69 Cr
Material₹26.21 Cr
Trend · statewide

—
—
Slowest spending this week · worth a look
Ashok Nagar — Chanderi ₹0
Top 10 new work types

Ranked by sanctioned cost

Breakdown

By district

Amounts in ₹ Crore