Ongoing works

Works in progress: what they cost, what has been spent, and how fast spending is moving.

MGNREGAConstruction of Well
58.3%
OF COST SPENT
₹46.03 L spent
of ₹78.91 L sanctioned
₹32.88 L still to spend
on 22 ongoing works
Works ongoing
22
Open the list of these works →
Sanctioned
₹78.91 L
Pure scheme (wage + material)
Expenditure since inception
₹46.03 L
58.3% of sanction
Balance cost (unspent)
₹32.88 L
Wage₹6.42 L
Material₹26.46 L
Trend · statewide

—
—
Top 10 new work types

Ranked by sanctioned cost

Breakdown

By GP

Amounts in ₹ Lakh