Ongoing works

Works in progress: what they cost, what has been spent, and how fast spending is moving.

MGNREGA + VBGRAMGConstruction of Road and Culvert
51.6%
OF COST SPENT
₹8.45 Cr spent
of ₹16.39 Cr sanctioned
₹7.94 Cr still to spend
on 106 ongoing works
Works ongoing
106
Open the list of these works →
Sanctioned
₹16.39 Cr
Pure scheme (wage + material)
Expenditure since inception
₹8.45 Cr
51.6% of sanction
Balance cost (unspent)
₹7.94 Cr
Wage₹1.55 Cr
Material₹6.39 Cr
Trend · statewide

—
—
Slowest spending this week · worth a look
Alirajpur — Jobat ₹0
Top 10 new work types

Ranked by sanctioned cost

Breakdown

By new work type

Amounts in ₹ Crore