Ongoing works

Works in progress: what they cost, what has been spent, and how fast spending is moving.

MGNREGA + VBGRAMG
32.7%
OF COST SPENT
₹6.52 Cr spent
of ₹19.93 Cr sanctioned
₹13.42 Cr still to spend
on 1,049 ongoing works
Works ongoing
1,049
Open the list of these works →
Sanctioned
₹19.93 Cr
Pure scheme (wage + material)
Expenditure since inception
₹6.52 Cr
32.7% of sanction
Balance cost (unspent)
₹13.42 Cr
Wage₹6.93 Cr
Material₹6.49 Cr
Trend · statewide

—
—
Slowest spending this quarter · worth a look
Rewa — Gangev −₹42.23 L
Top 10 new work types

Ranked by sanctioned cost

Breakdown

By GP

Amounts in ₹ Crore