Ongoing works

Works in progress: what they cost, what has been spent, and how fast spending is moving.

MGNREGA + VBGRAMGConstr of Cement Concrete Roads
49.8%
OF COST SPENT
₹2.02 Cr spent
of ₹4.06 Cr sanctioned
₹2.04 Cr still to spend
on 533 ongoing works
Works ongoing
533
Open the list of these works →
Sanctioned
₹4.06 Cr
Pure scheme (wage + material)
Expenditure since inception
₹2.02 Cr
49.8% of sanction
Balance cost (unspent)
₹2.04 Cr
Wage₹2.04 Cr
Material₹31,590
Trend · statewide

—
—
Slowest spending this week · worth a look
Sidhi — Sihawal −₹1.52 Cr
Top 10 new work types

Ranked by sanctioned cost

Breakdown

By block

Amounts in ₹ Lakh