Ongoing works

Works in progress: what they cost, what has been spent, and how fast spending is moving.

MGNREGA + VBGRAMGConstruction of Road and Culvert
82.7%
OF COST SPENT
₹3.93 Cr spent
of ₹4.76 Cr sanctioned
₹82.44 L still to spend
on 35 ongoing works
Works ongoing
35
Open the list of these works →
Sanctioned
₹4.76 Cr
Pure scheme (wage + material)
Expenditure since inception
₹3.93 Cr
82.7% of sanction
Balance cost (unspent)
₹82.44 L
Wage₹32.17 L
Material₹50.27 L
Trend · statewide

—
—
Slowest spending this week · worth a look
Sidhi — Sihawal −₹1.52 Cr
Top 10 new work types

Ranked by sanctioned cost

Breakdown

By new work type

Amounts in ₹ Crore