Ongoing works

Works in progress: what they cost, what has been spent, and how fast spending is moving.

MGNREGA + VBGRAMGConstruction of Road and Culvert
68.7%
OF COST SPENT
₹8.89 Cr spent
of ₹12.94 Cr sanctioned
₹4.05 Cr still to spend
on 104 ongoing works
Works ongoing
104
Open the list of these works →
Sanctioned
₹12.94 Cr
Pure scheme (wage + material)
Expenditure since inception
₹8.89 Cr
68.7% of sanction
Balance cost (unspent)
₹4.05 Cr
Wage₹1.87 Cr
Material₹2.18 Cr
Trend · statewide

—
—
Slowest spending this FY · worth a look
Dhar — Tirla −₹8.26 Cr
Top 10 new work types

Ranked by sanctioned cost

Breakdown

By block

Amounts in ₹ Crore