Ongoing works

Works in progress: what they cost, what has been spent, and how fast spending is moving.

MGNREGA + VBGRAMGConstruction of Road and Culvert
70.5%
OF COST SPENT
₹5.44 Cr spent
of ₹7.72 Cr sanctioned
₹2.28 Cr still to spend
on 55 ongoing works
Works ongoing
55
Open the list of these works →
Sanctioned
₹7.72 Cr
Pure scheme (wage + material)
Expenditure since inception
₹5.44 Cr
70.5% of sanction
Balance cost (unspent)
₹2.28 Cr
Wage₹1.41 Cr
Material₹86.83 L