Ongoing works

Works in progress: what they cost, what has been spent, and how fast spending is moving.

MGNREGALand Development
39.7%
OF COST SPENT
₹44.52 L spent
of ₹1.12 Cr sanctioned
₹67.51 L still to spend
on 34 ongoing works
Works ongoing
34
Open the list of these works →
Sanctioned
₹1.12 Cr
Pure scheme (wage + material)
Expenditure since inception
₹44.52 L
39.7% of sanction
Balance cost (unspent)
₹67.51 L
Wage₹37.64 L
Material₹29.87 L
Trend · statewide

—
—
Top 10 new work types

Ranked by sanctioned cost

Breakdown

By block

Amounts in ₹ Lakh