Ongoing works

Works in progress: what they cost, what has been spent, and how fast spending is moving.

MGNREGAConstruction of Road and Culvert
45.2%
OF COST SPENT
₹5.33 Cr spent
of ₹11.79 Cr sanctioned
₹6.46 Cr still to spend
on 72 ongoing works
Works ongoing
72
Open the list of these works →
Sanctioned
₹11.79 Cr
Pure scheme (wage + material)
Expenditure since inception
₹5.33 Cr
45.2% of sanction
Balance cost (unspent)
₹6.46 Cr
Wage₹2.70 Cr
Material₹3.76 Cr
Trend · statewide

—
—
Top 10 new work types

Ranked by sanctioned cost

Breakdown

By new work type

Amounts in ₹ Crore