Data as of 16 Oct 2026, 08:36 Admin login
FY
Reset

Ongoing works

Works in progress: what they cost, what has been spent, and how fast spending is moving.

MGNREGA
51.4%
OF COST SPENT
₹87.52 L spent
of ₹1.70 Cr sanctioned
₹82.90 L still to spend
on 18 ongoing works
Works ongoing
18
Open the list of these works →
Sanctioned
₹1.70 Cr
Pure scheme (wage + material)
Expenditure since inception
₹87.52 L
51.4% of sanction
Balance cost (unspent)
₹82.90 L
Wage₹59.90 L
Material₹23.00 L
Trend · statewide

—
—
Top 10 new work types

Ranked by sanctioned cost

Breakdown

By new work type

Amounts in ₹ Lakh