Ongoing works

Works in progress: what they cost, what has been spent, and how fast spending is moving.

MGNREGA + VBGRAMGConstr of Cement Concrete Roads
61.2%
OF COST SPENT
₹3.68 Cr spent
of ₹6.02 Cr sanctioned
₹2.34 Cr still to spend
on 171 ongoing works
Works ongoing
171
Open the list of these works →
Sanctioned
₹6.02 Cr
Pure scheme (wage + material)
Expenditure since inception
₹3.68 Cr
61.2% of sanction
Balance cost (unspent)
₹2.34 Cr
Wage₹1.47 Cr
Material₹86.27 L
Trend · statewide

—
—
Slowest spending this week · worth a look
Sidhi — Sihawal −₹1.52 Cr
Top 10 new work types

Ranked by sanctioned cost

Breakdown

By new work type

Amounts in ₹ Crore