Ongoing works

Works in progress: what they cost, what has been spent, and how fast spending is moving.

MGNREGA + VBGRAMGPlantation
31%
OF COST SPENT
₹17.52 Cr spent
of ₹56.61 Cr sanctioned
₹39.08 Cr still to spend
on 3,053 ongoing works
Works ongoing
3,053
Open the list of these works →
Sanctioned
₹56.61 Cr
Pure scheme (wage + material)
Expenditure since inception
₹17.52 Cr
31% of sanction
Balance cost (unspent)
₹39.08 Cr
Wage₹24.21 Cr
Material₹14.88 Cr
Trend · statewide

—
—
Slowest spending this week · worth a look
ASHOK NAGAR — CHANDERI ₹0
Top 10 new work types

Ranked by sanctioned cost

Breakdown

By block

Amounts in ₹ Crore