Ongoing works

Works in progress: what they cost, what has been spent, and how fast spending is moving.

MGNREGA + VBGRAMGConstruction of Road and Culvert
72.6%
OF COST SPENT
₹10.99 Cr spent
of ₹15.14 Cr sanctioned
₹4.15 Cr still to spend
on 57 ongoing works
Works ongoing
57
Open the list of these works →
Sanctioned
₹15.14 Cr
Pure scheme (wage + material)
Expenditure since inception
₹10.99 Cr
72.6% of sanction
Balance cost (unspent)
₹4.15 Cr
Wage₹2.28 Cr
Material₹1.87 Cr
Trend · statewide

—
—
Slowest spending this quarter · worth a look
Rewa — Gangev −₹42.23 L
Top 10 new work types

Ranked by sanctioned cost

Breakdown

By GP

Amounts in ₹ Lakh