Ongoing works

Works in progress: what they cost, what has been spent, and how fast spending is moving.

MGNREGA + VBGRAMGLand Development
56.9%
OF COST SPENT
₹7.45 Cr spent
of ₹13.08 Cr sanctioned
₹5.64 Cr still to spend
on 107 ongoing works
Works ongoing
107
Open the list of these works →
Sanctioned
₹13.08 Cr
Pure scheme (wage + material)
Expenditure since inception
₹7.45 Cr
56.9% of sanction
Balance cost (unspent)
₹5.64 Cr
Wage₹3.84 Cr
Material₹1.80 Cr
Trend · statewide

—
—
Slowest spending this week · worth a look
Sidhi — Sihawal −₹1.52 Cr
Top 10 new work types

Ranked by sanctioned cost

Breakdown

By block