Ongoing works

Works in progress: what they cost, what has been spent, and how fast spending is moving.

MGNREGA + VBGRAMGConstruction of Tank
42.2%
OF COST SPENT
₹23.06 Cr spent
of ₹54.65 Cr sanctioned
₹31.59 Cr still to spend
on 425 ongoing works
Works ongoing
425
Open the list of these works →
Sanctioned
₹54.65 Cr
Pure scheme (wage + material)
Expenditure since inception
₹23.06 Cr
42.2% of sanction
Balance cost (unspent)
₹31.59 Cr
Wage₹20.80 Cr
Material₹10.79 Cr
Trend · statewide

—
—
Slowest spending this week · worth a look
ASHOK NAGAR — CHANDERI ₹0
Top 10 new work types

Ranked by sanctioned cost

Breakdown

By block

Amounts in ₹ Crore