Ongoing works

Works in progress: what they cost, what has been spent, and how fast spending is moving.

MGNREGA + VBGRAMGCattle Shed
57.4%
OF COST SPENT
₹13.69 Cr spent
of ₹23.85 Cr sanctioned
₹10.16 Cr still to spend
on 241 ongoing works
Works ongoing
241
Open the list of these works →
Sanctioned
₹23.85 Cr
Pure scheme (wage + material)
Expenditure since inception
₹13.69 Cr
57.4% of sanction
Balance cost (unspent)
₹10.16 Cr
Wage₹1.08 Cr
Material₹9.08 Cr
Trend · statewide

—
—
Slowest spending this month · worth a look
Rewa — Gangev −₹42.23 L
Top 10 new work types

Ranked by sanctioned cost

Breakdown

By new work type

Amounts in ₹ Crore