Ongoing works

Works in progress: what they cost, what has been spent, and how fast spending is moving.

MGNREGA + VBGRAMGConstruction of Percolation Tank
39.9%
OF COST SPENT
₹69.16 Cr spent
of ₹173.34 Cr sanctioned
₹104.18 Cr still to spend
on 2,813 ongoing works
Works ongoing
2,813
Open the list of these works →
Sanctioned
₹173.34 Cr
Pure scheme (wage + material)
Expenditure since inception
₹69.16 Cr
39.9% of sanction
Balance cost (unspent)
₹104.18 Cr
Wage₹70.94 Cr
Material₹33.24 Cr
Trend · statewide

—
—
Slowest spending this week · worth a look
Sidhi — Sihawal −₹1.52 Cr
Top 10 new work types

Ranked by sanctioned cost

Breakdown

By new work type

Amounts in ₹ Crore