Ongoing works

Works in progress: what they cost, what has been spent, and how fast spending is moving.

MGNREGA + VBGRAMGTerracing
36.4%
OF COST SPENT
₹26.50 L spent
of ₹72.82 L sanctioned
₹46.32 L still to spend
on 19 ongoing works
Works ongoing
19
Open the list of these works →
Sanctioned
₹72.82 L
Pure scheme (wage + material)
Expenditure since inception
₹26.50 L
36.4% of sanction
Balance cost (unspent)
₹46.32 L
Wage₹23.69 L
Material₹22.63 L
Trend · statewide

—
—
Slowest spending this week · worth a look
Sidhi — Sihawal −₹1.52 Cr
Top 10 new work types

Ranked by sanctioned cost

Breakdown

By block

Amounts in ₹ Lakh