Ongoing works

Works in progress: what they cost, what has been spent, and how fast spending is moving.

MGNREGA + VBGRAMG
73.3%
OF COST SPENT
₹46.75 L spent
of ₹63.80 L sanctioned
₹17.05 L still to spend
on 31 ongoing works
Works ongoing
31
Open the list of these works →
Sanctioned
₹63.80 L
Pure scheme (wage + material)
Expenditure since inception
₹46.75 L
73.3% of sanction
Balance cost (unspent)
₹17.05 L
Wage₹5.59 L
Material₹11.46 L
Trend · statewide

—
—
Slowest spending this week · worth a look
Sidhi — Sihawal −₹1.52 Cr
Top 10 new work types

Ranked by sanctioned cost

Breakdown

By block

Amounts in ₹ Lakh