Ongoing works

Works in progress: what they cost, what has been spent, and how fast spending is moving.

MGNREGAPlantation
21%
OF COST SPENT
₹1.30 Cr spent
of ₹6.18 Cr sanctioned
₹4.88 Cr still to spend
on 292 ongoing works
Works ongoing
292
Open the list of these works →
Sanctioned
₹6.18 Cr
Pure scheme (wage + material)
Expenditure since inception
₹1.30 Cr
21% of sanction
Balance cost (unspent)
₹4.88 Cr
Wage₹2.34 Cr
Material₹2.54 Cr
Trend · statewide

—
—
Top 10 new work types

Ranked by sanctioned cost

Breakdown

By new work type

Amounts in ₹ Crore