Ongoing works

Works in progress: what they cost, what has been spent, and how fast spending is moving.

MGNREGAConstr of Cement Concrete Roads
77.9%
OF COST SPENT
₹5.69 Cr spent
of ₹7.31 Cr sanctioned
₹1.62 Cr still to spend
on 152 ongoing works
Works ongoing
152
Open the list of these works →
Sanctioned
₹7.31 Cr
Pure scheme (wage + material)
Expenditure since inception
₹5.69 Cr
77.9% of sanction
Balance cost (unspent)
₹1.62 Cr
Wage₹1.11 Cr
Material₹50.42 L
Trend · statewide

—
—
Slowest spending this FY · worth a look
Dhar — Tirla −₹10.48 Cr
Top 10 new work types

Ranked by sanctioned cost

Breakdown

By new work type

Amounts in ₹ Crore