Data as of 16 Oct 2026, 08:36 Admin login
FY
Reset

Ongoing works

Works in progress: what they cost, what has been spent, and how fast spending is moving.

MGNREGAConstruction of NADEP/Vermi Compost Pit
7.5%
OF COST SPENT
₹1,713 spent
of ₹22,938 sanctioned
₹21,225 still to spend
on 1 ongoing works
Works ongoing
1
Open the list of these works →
Sanctioned
₹22,938
Pure scheme (wage + material)
Expenditure since inception
₹1,713
7.5% of sanction
Balance cost (unspent)
₹21,225
Wage₹1,164
Material₹20,061
Trend · statewide

—
—
Top 10 new work types

Ranked by sanctioned cost

Breakdown

By block

Amounts in ₹ Rupees