Data as of 29 Oct 2026, 06:52 Admin login
FY
Reset

Ongoing works

Works in progress: what they cost, what has been spent, and how fast spending is moving.

VBGRAMGConstruction of Bund
0.2%
OF COST SPENT
₹17,400 spent
of ₹96.61 L sanctioned
₹96.44 L still to spend
on 53 ongoing works
Works ongoing
53
Open the list of these works →
Sanctioned
₹96.61 L
Pure scheme (wage + material)
Expenditure since inception
₹17,400
0.2% of sanction
Balance cost (unspent)
₹96.44 L
Wage₹67.42 L
Material₹29.02 L
Trend · statewide

—
—
Slowest spending this week · worth a look
Sidhi — Sihawal −₹1.52 Cr
Top 10 new work types

Ranked by sanctioned cost

Breakdown

By new work type

Amounts in ₹ Lakh