Ongoing works

Works in progress: what they cost, what has been spent, and how fast spending is moving.

MGNREGA + VBGRAMGConstruction of Road and Culvert
39%
OF COST SPENT
₹2.41 Cr spent
of ₹6.18 Cr sanctioned
₹3.77 Cr still to spend
on 41 ongoing works
Works ongoing
41
Open the list of these works →
Sanctioned
₹6.18 Cr
Pure scheme (wage + material)
Expenditure since inception
₹2.41 Cr
39% of sanction
Balance cost (unspent)
₹3.77 Cr
Wage₹61.44 L
Material₹3.15 Cr
Trend · statewide

—
—
Slowest spending this week · worth a look
Ashok Nagar — Chanderi ₹0
Top 10 new work types

Ranked by sanctioned cost

Breakdown

By GP

Amounts in ₹ Lakh