Ongoing works

Works in progress: what they cost, what has been spent, and how fast spending is moving.

MGNREGA + VBGRAMGConstruction of Road and Culvert
41.9%
OF COST SPENT
₹3.53 Cr spent
of ₹8.43 Cr sanctioned
₹4.90 Cr still to spend
on 66 ongoing works
Works ongoing
66
Open the list of these works →
Sanctioned
₹8.43 Cr
Pure scheme (wage + material)
Expenditure since inception
₹3.53 Cr
41.9% of sanction
Balance cost (unspent)
₹4.90 Cr
Wage₹2.39 Cr
Material₹2.51 Cr
Trend · statewide

—
—
Slowest spending this week · worth a look
Sidhi — Sihawal −₹1.52 Cr
Top 10 new work types

Ranked by sanctioned cost

Breakdown

By new work type

Amounts in ₹ Crore