Ongoing works

Works in progress: what they cost, what has been spent, and how fast spending is moving.

MGNREGA + VBGRAMG
46.6%
OF COST SPENT
₹29.82 Cr spent
of ₹63.93 Cr sanctioned
₹34.11 Cr still to spend
on 4,122 ongoing works
Works ongoing
4,122
Open the list of these works →
Sanctioned
₹63.93 Cr
Pure scheme (wage + material)
Expenditure since inception
₹29.82 Cr
46.6% of sanction
Balance cost (unspent)
₹34.11 Cr
Wage₹14.17 Cr
Material₹19.94 Cr
Trend · statewide

—
—
Slowest spending this week · worth a look
Sidhi — Sihawal −₹1.52 Cr
Top 10 new work types

Ranked by sanctioned cost

Breakdown

By new work type

Amounts in ₹ Crore