Ongoing works in MGNREGA + VB-G RAM G

Works in progress: what they cost, what has been spent, and how fast spending is moving.

MGNREGA + VBGRAMG
26.8%
OF COST SPENT
₹5.98 L spent
of ₹22.26 L sanctioned
₹16.29 L still to spend
on 27 ongoing works
Works ongoing
27
Open the list of these works →
Sanctioned
₹22.26 L
Pure scheme (wage + material)
Expenditure since inception
₹5.98 L
26.8% of sanction
Balance cost (unspent)
₹16.29 L
Wage₹7.98 L
Material₹8.31 L
Trend · statewide

—
—
Slowest spending this FY · worth a look
Dhar — Tirla −₹8.26 Cr
Top 10 new work types

Ranked by sanctioned cost

Breakdown

By block

Amounts in ₹ Lakh