Ongoing works

Works in progress: what they cost, what has been spent, and how fast spending is moving.

MGNREGA + VBGRAMG
49.3%
OF COST SPENT
₹102.90 Cr spent
of ₹208.62 Cr sanctioned
₹105.72 Cr still to spend
on 8,433 ongoing works
Works ongoing
8,433
Open the list of these works →
Sanctioned
₹208.62 Cr
Pure scheme (wage + material)
Expenditure since inception
₹102.90 Cr
49.3% of sanction
Balance cost (unspent)
₹105.72 Cr
Wage₹43.43 Cr
Material₹62.28 Cr
Trend · statewide

—
—
Slowest spending this month · worth a look
Rewa — Gangev −₹42.23 L
Top 10 new work types

Ranked by sanctioned cost

Breakdown

By block