Ongoing works

Works in progress: what they cost, what has been spent, and how fast spending is moving.

MGNREGA + VBGRAMGLand Development
35%
OF COST SPENT
₹9.52 L spent
of ₹27.24 L sanctioned
₹17.72 L still to spend
on 12 ongoing works
Works ongoing
12
Open the list of these works →
Sanctioned
₹27.24 L
Pure scheme (wage + material)
Expenditure since inception
₹9.52 L
35% of sanction
Balance cost (unspent)
₹17.72 L
Wage₹11.64 L
Material₹6.08 L
Trend · statewide

—
—
Slowest spending this week · worth a look
ASHOK NAGAR — CHANDERI ₹0
Top 10 new work types

Ranked by sanctioned cost

Breakdown