Ongoing works

Works in progress: what they cost, what has been spent, and how fast spending is moving.

MGNREGA + VBGRAMGCattle Shed
64.2%
OF COST SPENT
₹3.28 Cr spent
of ₹5.12 Cr sanctioned
₹1.83 Cr still to spend
on 15 ongoing works
Works ongoing
15
Open the list of these works →
Sanctioned
₹5.12 Cr
Pure scheme (wage + material)
Expenditure since inception
₹3.28 Cr
64.2% of sanction
Balance cost (unspent)
₹1.83 Cr
Wage₹13.90 L
Material₹1.69 Cr
Trend · statewide

—
—
Slowest spending this FY · worth a look
Bhind — Ater ₹15.77 L
Top 10 new work types

Ranked by sanctioned cost

Breakdown

By block

Amounts in ₹ Crore